One of the first questions Dublin homeowners ask us is how long the whole process takes โ€” from first enquiry to finished room. The honest answer depends on the type of conversion, but here's a full breakdown.

Timeline by Conversion Type

Conversion TypeTypical Duration
Velux / Rooflight3 โ€“ 5 weeks
Rear Dormer6 โ€“ 10 weeks
Hip-to-Gable8 โ€“ 12 weeks
Mansard12 โ€“ 16 weeks

The Full Process: Step by Step

1
Free Survey (Week 0)
We visit the property, assess suitability, measure up and discuss your requirements. Usually takes 30โ€“45 minutes.
2
Quote & Design (Week 1โ€“2)
Full itemised quote provided. Structural engineer engaged for drawings. Planning exemption confirmed or application submitted if required.
3
Materials Order & Start Date (Week 2โ€“3)
Materials ordered and start date agreed. Party wall notices served if applicable.
4
Structural Work (Week 1โ€“3 on site)
Steel beams, structural carpentry, dormer frame. Roof opened and made weathertight quickly โ€” usually within 2โ€“3 days.
5
First Fix (Week 3โ€“5 on site)
Insulation, electrics, plumbing (if en-suite), staircase installation.
6
Plastering & Finishing (Week 5โ€“8 on site)
Dry-lining, plastering, second fix electrics, windows, flooring preparation.
7
Sign-off & Certification
Building regulation inspection and Certificate of Compliance issued.

๐Ÿ’ก The roof is opened and made weathertight within 2โ€“3 days. You won't be left with an exposed roof overnight.

What Can Delay an Attic Conversion?

Can I Stay in the House During the Work?

Yes โ€” in almost all cases. The work is carried out from above and through the attic hatch. The main disruption is the staircase installation, which typically takes 1โ€“2 days. Most Dublin families stay in the house throughout the entire conversion.

Get a Free Quote & Timeline

Book a free survey and we'll give you an exact timeline and full quote for your property.

Book Free Survey